According to Louisiana Civil Code Article 2762, what is the prescription period for actions against contractors for defects in construction?

Correct Answer

C) 10 years from completion

Louisiana Civil Code Article 2762 establishes a 10-year prescription period for actions against contractors for defects in construction work.

Answer Options
A
5 years from completion
B
1 year from discovery of defect
C
10 years from completion
D
15 years from completion

Why This Is the Correct Answer

Louisiana Civil Code Article 2762 establishes a 10-year prescriptive period (sometimes called the 'decennial liability' rule) for actions against contractors (and architects) for defects in immovable property (real estate). This period runs from the date of substantial completion of the work. This is one of the longest construction liability windows in the U.S. and is a distinctive feature of Louisiana's French-derived civil law system. The rule is strict — it applies regardless of whether the owner discovered the defect, and it covers total ruin or major defects threatening the stability or integrity of the structure.

Why the Other Options Are Wrong

Option A: 5 years from completion

5 years from completion is not the Louisiana prescription period under Article 2762. It might be confused with shorter limitation periods in other states or with different types of claims (e.g., contract claims), but it is not the correct period for construction defect liability under the Louisiana Civil Code.

Option B: 1 year from discovery of defect

1 year from discovery of defect describes a discovery-based 'occurrence rule' found in some states' tort law frameworks. Louisiana's Article 2762 prescription runs from completion, not from discovery of the defect. This makes it an absolute period — once 10 years passes from completion, the claim is barred regardless of when (or whether) the defect was discovered.

Option D: 15 years from completion

15 years from completion exceeds the Article 2762 period. There is no standard Louisiana construction defect liability period of 15 years. This option may be a distractor designed to test whether candidates know the exact period or simply guess 'a long time.'

Memory Technique

'Decennial' means 10-year. Article 2762 = Louisiana's Decennial Liability = 10 years from completion. Associate the number 2762 with '10': 2+7 = 9, 6+2 = 8 — or simply remember 'LA 2762 = Ten-Year Rule.' Louisiana's French civil law heritage means it uses special terms like 'prescription' (not 'statute of limitations') and 'decennial liability.'

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.