According to Hawaii Building Code, what is the required design wind speed for hurricane-resistant construction in most coastal areas of Hawaii?

Correct Answer

D) 150 mph

Hawaii Building Code specifies 150 mph design wind speeds for most coastal areas to account for hurricane conditions and ensure structural integrity.

Answer Options
A
105 mph
B
180 mph
C
130 mph
D
150 mph

Why This Is the Correct Answer

The Hawaii State Building Code (based on IBC with Hawaii-specific amendments) requires a design wind speed of 150 mph for most coastal areas to account for hurricane exposure. Hawaii is in a high-wind zone due to its location in the central Pacific hurricane belt. The 150 mph value is the basic design wind speed (3-second gust, Risk Category II) used for structural design in the dominant coastal exposure zones.

Why the Other Options Are Wrong

Option A: 105 mph

105 mph is typical of inland or sheltered areas in lower wind exposure categories in mainland U.S. jurisdictions. It falls far below the requirements for Hawaii's hurricane-prone coastal zones and would result in dangerously under-designed structures.

Option B: 180 mph

180 mph is at the extreme upper end, applicable to the most exposed coastal zones in the highest-risk hurricane regions (such as parts of Florida and the Gulf Coast). While some specific Hawaii locations may have elevated design requirements, 180 mph is not the standard for most coastal areas statewide.

Option C: 130 mph

130 mph is a transitional wind speed used in moderate hurricane exposure zones. While closer to correct, it still falls short of Hawaii's 150 mph coastal requirement and would not meet code for structures in most Hawaiian coastal areas.

Was this explanation helpful?

More Hawaii Questions

A concrete mix design for coastal construction specifies a water-cement ratio of 0.40. If 650 lbs of cement is used per cubic yard, how many gallons of water should be added?

A contractor is installing hurricane straps rated at 1,500 pounds each. If the calculated uplift force on a rafter is 3,200 pounds, how many straps are required with a 2.0 safety factor?

Hawaii Building Code requires special inspection for concrete placement in seismic design categories. What is the minimum frequency for concrete strength testing?

What is the maximum allowable deflection for roof rafters under design wind loads in Hawaii's hurricane zones?

Which roofing attachment method is specifically required in Hawaii's hurricane zones for asphalt shingles on residential construction?

A building in Maui requires hurricane straps rated for 175 mph winds. If each strap must resist 1,200 lbs of uplift force and you have 48 roof-to-wall connections, what is the total uplift resistance provided?

During construction of a beachfront property, you notice white crystalline deposits forming on the concrete surface. This indicates:

You discover expansive clay soil conditions during excavation for a residential foundation in Kona. The plasticity index is 28. What foundation system is most appropriate?

According to Hawaii building requirements, hurricane straps connecting roof trusses to wall plates must be rated for what minimum uplift force in high wind zones?

A concrete slab foundation in Hawaii requires a vapor barrier. Due to high humidity and frequent rainfall, what type of vapor barrier is most appropriate?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.