EstatePass
Contract AdminContractsmedium40% of exam part

According to AIA Document A201, when must the contractor provide written notice to the architect of any claim for additional time or money?

Correct Answer

C) Within 21 days after occurrence of the event giving rise to the claim

AIA A201 requires contractors to provide written notice of claims within 21 days after the occurrence of the event or first observance of the condition giving rise to the claim. This timely notice requirement is critical for preserving claim rights.

Answer Options
A
Within 30 days after occurrence of the event giving rise to the claim
B
Before substantial completion of the project
C
Within 21 days after occurrence of the event giving rise to the claim
D
Within 10 days after occurrence of the event giving rise to the claim

Why This Is the Correct Answer

AIA Document A201, General Conditions of the Contract for Construction, specifically requires contractors to provide written notice of claims for additional time or money within 21 days after the occurrence of the event or first observance of the condition giving rise to the claim. This 21-day notice requirement is a critical procedural safeguard that protects both parties by ensuring timely communication of potential claims. Failure to provide this notice within the specified timeframe can result in waiver of the contractor's right to pursue the claim. This requirement allows the architect and owner to investigate the claim while the facts are fresh and potentially mitigate damages.

Why the Other Options Are Wrong

Option A: Within 30 days after occurrence of the event giving rise to the claim

30 days is longer than the actual requirement in AIA A201. While this might seem like a reasonable timeframe, the document specifically requires notice within 21 days, not 30 days.

Option B: Before substantial completion of the project

10 days is too short a timeframe and is not the requirement specified in AIA A201. While some contracts may have shorter notice periods, the standard AIA A201 document specifically requires 21 days.

Option D: Within 10 days after occurrence of the event giving rise to the claim

This option is far too vague and extends the notice period unreasonably. Substantial completion could occur months or years after the claim-triggering event, which would defeat the purpose of timely notice and make claim investigation and resolution much more difficult.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.