EstatePass
Contract AdminPermitsmedium20% of exam part

A general contractor is building a 3,500 square foot commercial office building. The building permit fee is $2.50 per square foot for the first 2,000 square feet and $1.75 per square foot for each additional square foot. What is the total building permit fee?

Correct Answer

A) $7,625

First 2,000 sq ft: 2,000 × $2.50 = $5,000. Remaining 1,500 sq ft: 1,500 × $1.75 = $2,625. Total: $5,000 + $2,625 = $7,625.

Answer Options
A
$7,625
B
$7,625
C
$8,125
D
$7,625

Why This Is the Correct Answer

This is a tiered fee calculation problem that requires breaking down the total square footage into different rate categories. The first 2,000 square feet are charged at $2.50 per square foot, while the remaining 1,500 square feet (3,500 - 2,000) are charged at the lower rate of $1.75 per square foot. Adding these two amounts together gives the correct total permit fee of $7,625.

Why the Other Options Are Wrong

Option B: $7,625

This answer likely results from incorrectly applying the higher rate ($2.50) to the entire 3,500 square feet instead of using the tiered structure, or from making an arithmetic error in the calculation.

Memory Technique

Remember 'TIER-ED' fees: Tiered rates require Identifying breakpoints, Evaluating each section separately, and Remembering to add Each Division together

Reference Hint

Florida Building Code Chapter 1 - Scope and Administration, specifically sections dealing with permit fees and fee schedules

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.