A Virginia contractor is installing a septic system and encounters groundwater at 8 feet depth. The USBC requires a minimum separation of 2 feet between the bottom of the drain field and groundwater. If the drain field requires 18 inches of depth, what is the maximum depth for the top of the drain field?
Correct Answer
C) 4.5 feet
Groundwater at 8 feet minus 2 feet separation minus 1.5 feet drain field depth = 4.5 feet maximum depth for top of drain field.
Why This Is the Correct Answer
Work backward from the groundwater level: Groundwater is at 8.0 ft. The bottom of the drain field must be at least 2.0 ft above groundwater, so the bottom of the drain field can be no deeper than 8.0 − 2.0 = 6.0 ft. The drain field itself is 18 inches (1.5 ft) deep, so the top of the drain field is at 6.0 − 1.5 = 4.5 ft maximum depth.
Why the Other Options Are Wrong
Option A: 6.0 feet
6.0 feet is the maximum allowable depth for the BOTTOM of the drain field (groundwater depth minus the 2-foot separation buffer). The question asks for the top of the drain field, which must be 1.5 feet shallower than the bottom.
Option B: 5.0 feet
5.0 feet does not correspond to any step in the correct calculation. It may result from subtracting only 3 feet total from the 8-foot groundwater depth without accounting for the correct field depth of 1.5 feet.
Option D: 5.5 feet
5.5 feet results from subtracting only 1 foot (half the drain field depth) instead of the full 1.5 feet from the 6.0-foot bottom limit. This represents an arithmetic error in the final subtraction step.
Memory Technique
Use three steps: (1) Bottom limit = Groundwater − Separation = 8 − 2 = 6 ft. (2) Convert field depth: 18 in = 1.5 ft. (3) Top limit = Bottom limit − Field depth = 6 − 1.5 = 4.5 ft. Write the three-step chain on scratch paper before solving.
More Virginia Questions
Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?
A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?
A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?
A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?
Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?
A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?
A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?
A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?
Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.
A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?