EstatePass
Contract AdminContractsmedium40% of exam part

A time and materials contract specifies labor at $85 per hour with a 1.5 multiplier for overtime. If a worker works 45 hours in one week (with 5 hours overtime), what is the total labor charge?

Correct Answer

D) $4,037.50

Regular time: 40 hours × $85 = $3,400. Overtime: 5 hours × $85 × 1.5 = $637.50. Total: $3,400 + $637.50 = $4,037.50.

Answer Options
A
$4,250
B
$3,825
C
$4,462.50
D
$4,037.50

Why This Is the Correct Answer

The calculation correctly separates regular time from overtime hours and applies the appropriate rates. Regular time is calculated as 40 hours × $85 = $3,400, while overtime uses the 1.5 multiplier: 5 hours × $85 × 1.5 = $637.50. The total labor charge is the sum of both: $3,400 + $637.50 = $4,037.50.

Why the Other Options Are Wrong

Option A: $4,250

This answer ($3,825) appears to use an incorrect calculation method, possibly applying a uniform rate without properly accounting for the overtime multiplier of 1.5.

Option C: $4,462.50

This answer ($4,462.50) significantly overcharges and likely applies an incorrect multiplier or calculation method to the total hours worked.

Memory Technique

Remember 'ROTO': Regular first (40 hrs), Overtime second (excess hrs), Total multiplier (1.5), Overall sum - always keep regular and overtime separate in your calculations.

Reference Hint

Florida Building Contractor Reference Manual - Contract Administration and Labor Cost Calculations chapter

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.