A contractor completes $50,000 worth of work in a billing period. If the contract specifies 10% retainage, what amount should be requested in the payment application?

Correct Answer

C) $45,000

With 10% retainage, the owner withholds 10% of each payment until project completion. Therefore, $50,000 × 0.90 = $45,000 should be requested in the payment application, with $5,000 held as retainage.

Answer Options
A
$40,000
B
$55,000
C
$45,000
D
$50,000

Why This Is the Correct Answer

Retainage is a percentage of each payment that the owner withholds until project completion to ensure the contractor fulfills all obligations. When a contract specifies 10% retainage, the contractor can only request 90% of the work completed in each billing period. Therefore, from $50,000 worth of completed work, the contractor requests $45,000 while $5,000 is held as retainage. This protects the owner and ensures the contractor returns to complete any punch list items.

Why the Other Options Are Wrong

Option B: $55,000

This amount ($40,000) would represent 20% retainage, not the 10% specified in the contract. This calculation error would result in the contractor requesting $10,000 less than entitled.

Option D: $50,000

This amount ($50,000) represents requesting 100% of the work completed, which ignores the 10% retainage requirement entirely. The owner would reject this payment application as it doesn't comply with the contract terms.

Memory Technique

Remember 'R.A.P.' - Retainage Always Protects the owner. The contractor gets paid the work amount MINUS the retainage, never the full amount until project completion.

Reference Hint

Florida Building Code, Chapter 1, Section 107 - Fees and Permits, or contract administration sections dealing with progress payments and retainage

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.