EstatePass
Contract AdminPermitsmedium20% of exam part

A Temporary Certificate of Occupancy is typically issued for what maximum time period?

Correct Answer

C) 90 days

A Temporary Certificate of Occupancy is typically issued for a maximum of 90 days to allow occupancy while minor items are completed. Extensions may be possible but require justification and approval.

Answer Options
A
180 days
B
60 days
C
90 days
D
30 days

Why This Is the Correct Answer

A Temporary Certificate of Occupancy (TCO) is issued for a maximum of 90 days under Florida Building Code provisions. This timeframe allows property owners to occupy a building while completing minor finishing work or addressing non-critical code compliance items. The 90-day period provides sufficient time to resolve outstanding issues without creating undue hardship for occupants. Extensions beyond 90 days are possible but require formal application and justification to the building official.

Why the Other Options Are Wrong

Option B: 60 days

60 days, while closer to the correct answer, is still shorter than the standard 90-day maximum period established by the Florida Building Code.

Option D: 30 days

30 days is too short a timeframe for most construction projects to complete remaining work items that would warrant a TCO issuance.

Memory Technique

Think '90 days = 3 months = 1 quarter year' - enough time to wrap up a construction project's final details but not so long that safety becomes a concern.

Reference Hint

Florida Building Code, Chapter 1, Section 110 - Certificate of Occupancy provisions

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.