EstatePass
Contract AdminContractseasy40% of exam part

A general contractor receives a change order request that will add $25,000 to the contract price and extend the completion date by 10 days. The contract allows for a 10% markup on change order work. What should be the total change order amount?

Correct Answer

A) $27,500

The change order amount includes the direct costs plus the allowed markup: $25,000 + ($25,000 × 0.10) = $25,000 + $2,500 = $27,500. The time extension is handled separately from the cost calculation.

Answer Options
A
$27,500
B
$30,000
C
$35,000
D
$25,000

Why This Is the Correct Answer

Option B is correct because change orders must include both the direct cost of the additional work and any contractually allowed markup. The $25,000 represents the base cost of the change order work, and the contract specifically allows for a 10% markup on change order work. This markup compensates the contractor for overhead and profit on the additional scope. The time extension is a separate consideration that doesn't affect the monetary calculation.

Why the Other Options Are Wrong

Option B: $30,000

Option A only includes the direct cost of $25,000 without applying the contractually allowed 10% markup, which would shortchange the contractor's entitled compensation.

Option C: $35,000

Option D applies a 40% markup ($25,000 × 1.40 = $35,000) which is significantly higher than the contractually allowed 10% markup and would be an overcharge.

Memory Technique

Remember 'Base + Markup = Total' - think of it like adding tax to a purchase, but here you're adding the contractor's allowed profit margin to the direct costs.

Reference Hint

Florida Building Code - Administrative Chapter 1, Section on Contract Modifications and Change Orders, or AIA Document A201 General Conditions regarding change order pricing

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.