North CarolinaNC Supplementhard100% of exam part

A subcontractor working on a public school project in NC has not been paid by the general contractor. Under NC public works lien law, when must the Notice to Lien Agent be filed?

Correct Answer

D) Before starting work on the project

NC public works lien law requires subcontractors to file Notice to Lien Agent before starting work on the project to preserve lien rights.

Answer Options
A
Within 30 days of first furnishing labor or materials
B
Within 45 days of first furnishing labor or materials
C
Within 15 days of first furnishing labor or materials
D
Before starting work on the project

Why This Is the Correct Answer

NC public works lien law requires that a Notice to Lien Agent be filed BEFORE starting work on the project. This is a strict prerequisite to preserve lien rights on public projects — timing is earlier than what most people assume because the clock does not start at first furnishing; it must be done in advance.

Why the Other Options Are Wrong

Option A: Within 30 days of first furnishing labor or materials

Option A ('Within 30 days of first furnishing labor or materials') is incorrect. The 30-day window applies to private construction lien notices, not public works projects. Public works lien preservation begins before any work, not after.

Option B: Within 45 days of first furnishing labor or materials

Option B ('Within 45 days of first furnishing labor or materials') is incorrect. No 45-day window exists for this purpose under NC public works lien law. This is a fabricated timeframe likely intended to confuse test-takers familiar with general lien deadlines.

Option C: Within 15 days of first furnishing labor or materials

Option C ('Within 15 days of first furnishing labor or materials') is incorrect. No 15-day rule governs Notice to Lien Agent filings. This distracter mimics other short-deadline rules in construction law but does not apply here.

Memory Technique

Think 'Public First': on PUBLIC projects, you must file FIRST — before you ever set foot on the site. Private projects allow you to file after the fact, but public projects demand the paperwork before the boots hit the ground.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.