A subcontractor provides preliminary notice on a Louisiana private project on March 1st. The subcontractor's last day of work was June 15th. What is the deadline to file the lien claim?
Correct Answer
B) August 14th
Under Louisiana's Private Works Act, lien claims must be filed within 60 days of the last day of work. June 15th + 60 days = August 14th.
Why This Is the Correct Answer
Under Louisiana's Private Works Act, lien claims must be filed within 60 days of the last day of work. June 15th + 60 days = August 14th.
More la-supplement Questions
A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?
A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?
A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?
Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?
A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?
Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?
Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?
A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?
A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?
A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor is building a residential project in Louisiana and discovers asbestos-containing materials during demolition. According to Louisiana environmental regulations, what is the first required action?
Next Question
Calculate the lien amount a subcontractor can claim in Louisiana. Subcontract amount: $45,000. Work completed: 80%. Payments received: $25,000. What is the maximum lien claim?