EstatePass
LouisianaLA Supplementmedium100% of exam part

A subcontractor provides preliminary notice on a Louisiana private project on March 1st. The subcontractor's last day of work was June 15th. What is the deadline to file the lien claim?

Correct Answer

B) August 14th

Under Louisiana's Private Works Act, lien claims must be filed within 60 days of the last day of work. June 15th + 60 days = August 14th.

Answer Options
A
July 15th
B
August 14th
C
August 15th
D
September 14th

Why This Is the Correct Answer

Under Louisiana's Private Works Act (R.S. 9:4822), a subcontractor must file a lien claim within 60 days of the last day of work. Counting 60 days from June 15th: June has 30 days, so 15 remaining days in June + 45 more days = July 31 + 14 days into August = August 14th.

Why the Other Options Are Wrong

Option A: July 15th

July 15th represents exactly 30 days after the last work date — half the allowed 60-day period. This would apply if Louisiana used a 30-day lien deadline, but the Private Works Act allows 60 days.

Option C: August 15th

August 15th is one day too late. This is a critical distinction: June 15 + 60 days = August 14, not August 15. Day counting errors on lien deadlines can result in losing lien rights entirely.

Option D: September 14th

September 14th represents 90 days from the last work date. Louisiana's Private Works Act deadline is 60 days, not 90 days. Some other states or the federal Miller Act use 90-day periods, which can cause confusion.

Memory Technique

Write out the count: June 15 → June 30 = 15 days. Need 45 more. July has 31 days: 15 + 31 = 46 days. One more day = August 1 = 47 days total — overshoot. Back to July 31 = 46 days, then add 14 more = August 14 = 60 days exactly.

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.