EstatePass
ArizonaAZ B&Leasy100% of exam part

A subcontractor provided $8,500 in materials and labor. The general contractor paid $6,000, leaving a balance of $2,500. If the subcontractor files a mechanics lien, what is the maximum lien amount that can be claimed?

Correct Answer

B) $2,500

Under Arizona lien law, the lien amount cannot exceed the amount actually owed for labor and materials furnished, which is $2,500.

Answer Options
A
$8,500
B
$2,500
C
$6,000
D
The amount depends on the contract terms

Why This Is the Correct Answer

Option B is correct. Under Arizona lien law, a mechanics lien can only be filed for the amount actually owed and unpaid. Since the general contractor paid $6,000 of the $8,500 owed, the remaining unpaid balance is $2,500. The lien cannot exceed the actual debt.

Why the Other Options Are Wrong

Option A: $8,500

$8,500 is the total contract value, not the amount owed. Filing a lien for the full contract amount when a partial payment has been received would be an overstatement of the debt and is not permitted under Arizona lien law.

Option C: $6,000

$6,000 is the amount already paid, not the amount owed. Confusing the paid amount with the lien amount is a common error. The lien protects the unpaid balance, not what has already been satisfied.

Option D: The amount depends on the contract terms

The lien amount is not discretionary based on contract terms — it is determined by statute as the actual unpaid amount for labor and materials furnished. Contract language cannot expand lien rights beyond what is legally owed.

Memory Technique

Lien = What You're Still Owed. The math: $8,500 billed − $6,000 paid = $2,500 lien. Think of the lien as a 'balance due' sticker placed on the property — it shows only the outstanding balance, not the original price tag.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.