A subcontractor has not been paid by the general contractor on a public project. Under NC lien law, what is the subcontractor's primary remedy?
Correct Answer
C) Make a claim against the payment bond
On public projects, subcontractors cannot file mechanics' liens but can make claims against the payment bond required for public construction projects.
Why This Is the Correct Answer
On public construction projects in North Carolina, subcontractors cannot file mechanics' liens against government-owned property because the government holds sovereign immunity and cannot have its property encumbered. Instead, NC requires general contractors on public projects above a certain threshold to obtain a payment bond. Subcontractors' primary remedy is to make a claim against this payment bond under NC G.S. 44A-27 et seq.
Why the Other Options Are Wrong
Option A: File a mechanics' lien on the property
Filing a mechanics' lien on the property is NOT available for public projects. Government-owned property (state, county, municipal) is immune from mechanics' liens. This remedy is only available on private property.
Option B: Sue the property owner directly
Suing the property owner (the government) directly is generally barred by sovereign immunity without specific statutory authorization. The payment bond system exists precisely as an alternative to direct suits against the government.
Option D: File a complaint with the licensing board
Filing a complaint with the licensing board is a disciplinary remedy against the contractor's license, not a payment remedy. The licensing board cannot compel payment or adjudicate payment disputes.
Memory Technique
Public = Bond. Private = Lien. The government owns the land and you cannot lien government land β so the bond is the substitute protection. Think 'Public Bond, Private Lien.'
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000: