A subcontractor files a lien claim in NC but fails to serve notice to the property owner within the required timeframe. What is the consequence?
Correct Answer
B) The lien becomes invalid and unenforceable
Under NC lien law, failure to properly serve notice to the property owner within required timeframes makes the lien invalid and unenforceable.
Why This Is the Correct Answer
Option B (the lien becomes invalid and unenforceable) is correct. Under NC lien law, proper and timely notice to the property owner is a mandatory procedural requirement. Failure to serve notice within the statutory timeframe is fatal to the lien — it becomes void and the subcontractor loses lien rights entirely.
Why the Other Options Are Wrong
Option A: A late fee is assessed but the lien remains valid
NC lien law does not provide for a late fee structure that preserves lien validity. Timely notice is a substantive requirement, not a procedural formality — there is no penalty fee option that saves an untimely lien.
Option C: The lien remains valid but with reduced priority
NC lien law does not create a reduced-priority category for late-noticed liens. The notice requirement is binary: proper and timely notice preserves the lien; failure to comply voids it. There is no middle-ground reduced priority status.
Option D: The lien is valid but limited to material costs only
NC lien law does not limit a defective lien to material costs only. Once the lien is invalidated by improper notice, it is entirely unenforceable — no partial recovery through the lien mechanism is available.
Memory Technique
NC lien = File AND Notice. Think of the lien as a two-key lock: you need both the filed claim AND proper owner notice to open it. Miss either key and the lien is locked out — invalid and unenforceable. No partial credit, no late fees.
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Calculate the lien amount a subcontractor can claim under NC lien law for a project where they were contracted for $28,000, completed $24,500 worth of work, and were paid $18,000:
Next Question
According to NC building codes, what is the minimum inspection requirement for residential foundation work?