A subcontractor completes work on February 10th but the general contractor doesn't make final payment until May 15th. Under Arizona lien law, what is the deadline for the subcontractor to file a lien?
Correct Answer
C) June 10th (120 days from completion)
Subcontractors must file liens within 120 days of completion of their work, regardless of when payment is received. February 10th + 120 days = June 10th.
Why This Is the Correct Answer
Under Arizona lien law, a subcontractor must record a lien within 120 days of the last date they provided labor or materials — not from the date of payment. The subcontractor completed work on February 10th. Adding 120 days: February has 18 remaining days (Feb 10 to Feb 28), March = 31, April = 30, May = 31 → 18 + 31 + 30 = 79 days through April, then 41 more days into June = June 10th. The payment date of May 15th is irrelevant to this calculation.
Why the Other Options Are Wrong
Option A: September 12th (120 days from final payment)
Option A ('September 12th — 120 days from final payment') is incorrect. The 120-day clock runs from the subcontractor's completion of work, not from when the general contractor makes payment. Using the May 15th payment date produces a wrong answer of September 12th.
Option B: July 15th (60 days from final payment)
Option B ('July 15th — 60 days from final payment') is incorrect for two reasons: (1) the trigger date is completion of work, not payment, and (2) Arizona allows 120 days for subcontractors to file liens — not 60 days.
Option D: August 15th (90 days from final payment)
Option D ('August 15th — 90 days from final payment') is incorrect. 90 days is not the correct lien filing period under Arizona law (it is 120 days), and the payment date is not the trigger event — completion of work is.
Memory Technique
Lien clock = Completion Clock. The moment a subcontractor sets down their tools for the last time, a 120-day countdown begins. Money coming in or not coming in has zero effect on that countdown.
More Arizona Questions
What is the current minimum bond amount required for a residential contractor license in Arizona?
A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?
Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?
Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?
A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?
A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?
According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?
A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?
A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?
A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A residential contractor's license is suspended by ROC. During the suspension period, what work can the contractor legally perform?
Next Question
Calculate the Arizona transaction privilege tax owed by a contractor on a project with gross receipts of $125,000, assuming a combined state and local rate of 8.6%.
