A subcontractor completes electrical work worth $3,200 on March 15th. The general contractor fails to pay. If the subcontractor wants to file a lien, what is the latest date they can file under ORS 87?

Correct Answer

C) July 13th

Under ORS 87, liens must be filed within 120 days of work completion. 120 days from March 15th is July 13th.

Answer Options
A
September 11th
B
May 29th
C
July 13th
D
June 13th

Why This Is the Correct Answer

Under ORS 87, mechanics' liens must be filed within 120 days of the date the claimant last performed labor or furnished materials. Counting 120 days from March 15th: March has 16 remaining days (March 15 + 16 = March 31), April adds 30 days (46), May adds 31 days (77), June adds 30 days (107), and 13 more days into July = July 13th. The deadline is July 13th.

Why the Other Options Are Wrong

Option A: September 11th

September 11th is far beyond the 120-day deadline. This would correspond to approximately 180 days from March 15th, which exceeds the lien filing window and would result in the lien being invalid.

Option B: May 29th

May 29th corresponds to approximately 75 days from March 15th, which is significantly short of the full 120-day period allowed. Filing then would be valid but is not the latest possible date.

Option D: June 13th

June 13th corresponds to 90 days from March 15th, not 120. This is a common error caused by confusing the 120-day lien period with a 90-day period used in some other states or lien contexts.

Memory Technique

120 days = 4 months. Start counting from the last day worked: 4 months later lands on the same day of the month. March 15 + 4 months = July 15, then subtract 2 days for the shorter months in between = July 13.

Was this explanation helpful?

More Oregon Questions

Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?

An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?

A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?

Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?

A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?

A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.

A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?

What is the minimum experience requirement for obtaining an Oregon CCB contractor license?

A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?

A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.