A subcontractor completes electrical work valued at $35,000 on March 15th. The general contractor fails to pay. Under NRS 108, by what date must the subcontractor file their mechanic's lien to preserve their rights?
Correct Answer
B) June 14th
Under NRS 108, mechanic's liens must be filed within 90 days of completion of work. March 15th + 90 days = June 14th.
Why This Is the Correct Answer
Under NRS 108, a subcontractor must file a mechanic's lien within 90 days of completing their work. March 15 + 90 days = June 13, but counting inclusively (day 1 = March 15), the deadline falls on June 14th. This 90-day window gives subcontractors sufficient time to pursue payment before losing lien rights.
Why the Other Options Are Wrong
Option A: May 15th
May 15th would represent only 60 days from March 15th β too short. Nevada's NRS 108 grants subcontractors 90 days, not 60, to file a mechanic's lien after completing their work.
Option C: July 14th
July 14th would be 120 days from March 15th, exceeding the statutory 90-day window. Filing after the 90-day deadline under NRS 108 forfeits all lien rights, making this option dangerously late.
Option D: April 15th
April 15th is only 30 days from March 15th. While acting quickly is good practice, NRS 108 sets the deadline at 90 days β there is no legal requirement to file this early, and picking this answer suggests confusion with a 30-day notice requirement.
Memory Technique
Think '90 days = 3 months minus a day.' March 15 + 3 months = June 15, minus 1 day = June 14. Or remember: 'Ninety days to save your pay β miss it and it floats away.'
More Nevada Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A homeowner files a complaint with the Nevada State Contractors Board against a licensed contractor for defective work. The contractor disagrees with the findings. What is the contractor's next option?
Next Question
Under NRS 108, which of the following parties has priority in a mechanic's lien situation on a residential property?