A subcontractor completes electrical work valued at $35,000 on March 15th. The general contractor fails to pay. Under NRS 108, by what date must the subcontractor file their mechanic's lien to preserve their rights?

Correct Answer

B) June 14th

Under NRS 108, mechanic's liens must be filed within 90 days of completion of work. March 15th + 90 days = June 14th.

Answer Options
A
May 15th
B
June 14th
C
July 14th
D
April 15th

Why This Is the Correct Answer

Under NRS 108, mechanic's liens must be filed within 90 days of completion of work. March 15th + 90 days = June 14th.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.