EstatePass
ArizonaAZ B&Lhard100% of exam part

A subcontractor completes electrical work valued at $12,000 on a commercial project. The general contractor fails to pay. Under Arizona lien law, who can the subcontractor serve with a preliminary 20-day notice?

Correct Answer

C) Both the property owner and general contractor

Under A.R.S. 33-981, subcontractors must serve preliminary 20-day notices to both the property owner and the general contractor to preserve lien rights.

Answer Options
A
Only the general contractor
B
Only the property owner
C
Both the property owner and general contractor
D
The construction lender only

Why This Is the Correct Answer

Under A.R.S. § 33-981, any person other than an original contractor who furnishes labor, materials, or services must serve a preliminary 20-day notice on BOTH the property owner and the general contractor (original contractor) to preserve their right to file a mechanics lien. Serving both parties ensures that the owner is aware of the subcontractor's involvement and potential lien exposure, and gives the GC an opportunity to remit payment.

Why the Other Options Are Wrong

Option A: Only the general contractor

Serving only the general contractor is insufficient. Arizona law requires the notice to reach the property owner as well, because the owner must be informed of lien exposure on their property. Without notifying the owner, the subcontractor loses lien rights against the property itself.

Option B: Only the property owner

Serving only the property owner is also insufficient. The general contractor must also receive the notice so they are formally put on notice of the subcontractor's claim and can address payment. Omitting the GC does not satisfy the statutory requirement.

Option D: The construction lender only

The construction lender is a separate party and is not the primary recipient required by A.R.S. § 33-981. While notice to the lender can be important in some financing contexts, it does not replace the mandatory notice to the property owner and general contractor.

Memory Technique

Think of the acronym 'OG' — Owner + General contractor. A sub always notifies the 'OG' duo within 20 days. If you skip either half of the OG, you lose your lien rights.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.