A subcontractor completes electrical work on March 15th and the owner occupies the building on April 1st. Under Nevada lien law (NRS 108), what is the last day the subcontractor can file a mechanics' lien?

Correct Answer

C) June 1st

Under NRS 108, subcontractors must file a mechanics' lien within 60 days after completion of the work of improvement, which is typically marked by occupancy. 60 days from April 1st is June 1st.

Answer Options
A
May 15th
B
July 1st
C
June 1st
D
June 14th

Why This Is the Correct Answer

Under NRS 108, subcontractors must file a mechanics' lien within 60 days after completion of the work of improvement, which is typically marked by occupancy. 60 days from April 1st is June 1st.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.