EstatePass
OregonOR B&Lhard100% of exam part

A subcontractor completes electrical work on February 15th. The general contractor stops all work on March 1st due to weather, then resumes April 10th and finishes the project May 20th. Under ORS 87, the subcontractor's lien filing deadline is:

Correct Answer

B) May 1st (75 days from completion)

The subcontractor has 75 days from their own work completion (Feb 15), making the deadline May 1st under ORS 87.

Answer Options
A
July 4th (75 days from project completion)
B
May 1st (75 days from completion)
C
August 3rd (75 days from final completion)
D
April 15th (60 days from completion)

Why This Is the Correct Answer

Option B is correct. Under ORS 87, a subcontractor's lien deadline runs from the last date the subcontractor personally provided labor or materials — not from the general contractor's project completion date. The electrical subcontractor finished on February 15th, so 75 days later is approximately May 1st. The general contractor's ongoing work or weather delays are irrelevant to the subcontractor's own deadline.

Why the Other Options Are Wrong

Option A: July 4th (75 days from project completion)

July 4th (75 days from project completion) is incorrect because a subcontractor's clock does not run from the general contractor's completion date (May 20th). Using the GC's finish date would give the subcontractor more time than ORS 87 allows.

Option C: August 3rd (75 days from final completion)

August 3rd (75 days from final completion) also incorrectly anchors the deadline to the GC's May 20th finish date, which is not the correct reference point for a subcontractor under ORS 87.

Option D: April 15th (60 days from completion)

April 15th (60 days from completion) is wrong in two ways: the lien period under ORS 87 is 75 days, not 60 days, and it miscounts from February 15th (60 days would be April 15th, but the correct period is 75 days = May 1st).

Memory Technique

Think of each trade as having their own personal stopwatch. The moment a sub puts down their tools for the last time, their 75-day timer starts. The GC's timer is separate. Your clock = your last day, your 75 days.

Was this explanation helpful?

More Oregon Questions

Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?

An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?

A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?

Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?

A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?

A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.

A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?

What is the minimum experience requirement for obtaining an Oregon CCB contractor license?

A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?

A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.