EstatePass
LouisianaLA Supplementhard100% of exam part

A subcontractor completed work on March 15th and sent preliminary notice on March 20th. Under Louisiana's Private Works Act, what is the last day to file a lien claim?

Correct Answer

B) May 14th

The 60-day period runs from completion of work (March 15th), not from when notice was sent. 60 days from March 15th is May 14th.

Answer Options
A
June 13th
B
May 14th
C
June 18th
D
May 19th

Why This Is the Correct Answer

Under Louisiana's Private Works Act, a claimant has 60 days from the last day work was performed (or materials were delivered) to file a lien claim. The clock starts on the date work was completed — March 15th — regardless of when preliminary notice was sent. Counting 60 days from March 15th: March has 16 remaining days after the 15th (March 16–31), April has 30 days (total 46), and 14 more days into May reaches May 14th. The preliminary notice date (March 20th) is irrelevant to the lien deadline calculation.

Why the Other Options Are Wrong

Option A: June 13th

June 13th would result from counting 90 days from March 15th, or from incorrectly starting the 60-day count from March 20th (the notice date) and adding extra days. Neither calculation reflects the correct starting date or duration under Louisiana law.

Option C: June 18th

June 18th results from starting the 60-day count from March 20th (the preliminary notice date) and adding 90 days, or from some other incorrect combination. The lien deadline runs from work completion, not notice.

Option D: May 19th

May 19th results from starting the 60-day count from March 20th (the preliminary notice date) rather than from March 15th (work completion date). The notice date is a distractor — the statute runs from the last day of work.

Memory Technique

Louisiana lien clock: START = last day of work, DURATION = 60 days. The notice date is a red herring. Drill the phrase: 'Work done + 60 days = lien deadline.'

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.