A residential project requires disturbing 2.5 acres of land. According to NC environmental regulations, what permit is required?
Correct Answer
A) Sedimentation and erosion control permit
NC environmental regulations require a sedimentation and erosion control permit for land disturbance of 1 acre or more.
Why This Is the Correct Answer
NC's Sedimentation Pollution Control Act requires a sedimentation and erosion control permit for any land-disturbing activity affecting 1 acre or more. At 2.5 acres, this project clearly exceeds the threshold. This permit requires an approved erosion control plan before land disturbance begins.
Why the Other Options Are Wrong
Option B: No permit required
Claiming no permit is required is incorrect. NC law sets a 1-acre threshold, and 2.5 acres of disturbance is well above it. Proceeding without a sedimentation and erosion control permit would be a regulatory violation.
Option C: Stormwater management permit only
A stormwater management permit alone is insufficient. While stormwater permits may also be required in certain circumstances, the primary required permit for land disturbance of this scale is the sedimentation and erosion control permit under the Sedimentation Pollution Control Act.
Option D: Environmental impact permit
An 'environmental impact permit' is not the specific NC mechanism for land disturbance projects. This terminology applies more to federal NEPA processes for major projects, not to typical residential construction in NC.
Memory Technique
NC's magic number: 1 ACRE triggers sedimentation and erosion control. Think 'Dirt Disturbed = Dirt Permit' β any job over 1 acre of earth-moving needs this permit.
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor in North Carolina fails to renew their license by the expiration date. What is the grace period before the license becomes invalid?
Next Question
A contractor in North Carolina completes work valued at $85,000 but has not been paid. If filing a mechanic's lien, what is the maximum amount that can be claimed under NC lien law?