EstatePass
ArizonaAZ B&Lmedium100% of exam part

A residential contractor in Arizona must maintain workers' compensation insurance. If a contractor has 2 employees and annual payroll of $85,000, what is the approximate minimum annual premium for workers' compensation coverage for general construction work (assuming a rate of $8.50 per $100 of payroll)?

Correct Answer

D) $7,225

Workers' compensation premium = ($85,000 ÷ $100) × $8.50 = 850 × $8.50 = $7,225.

Answer Options
A
$9,350
B
$6,825
C
$8,925
D
$7,225

Why This Is the Correct Answer

Workers' comp premium formula: (Payroll ÷ $100) × Rate = ($85,000 ÷ $100) × $8.50 = 850 × $8.50 = $7,225. The number of employees (2) is given as context but does not change the calculation — the premium is based on payroll, not headcount.

Why the Other Options Are Wrong

Option A: $9,350

$9,350 does not result from the correct formula. This may come from using a higher rate or misplacing the decimal (e.g., using $11.00 per $100 instead of $8.50).

Option B: $6,825

$6,825 is close but incorrect. It may result from dividing by a slightly different denominator or using $8.03 per $100 — a rounding or arithmetic error in applying the formula.

Option C: $8,925

$8,925 may result from using a rate of approximately $10.50 per $100 or from incorrectly treating the number of employees (2) as a multiplier in a non-standard calculation.

Memory Technique

Workers' Comp formula: Payroll ÷ 100 × Rate. Two steps, no exceptions. The number of employees is irrelevant to the calculation — only the total payroll matters.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.