A residential contractor in Arizona completes $45,000 worth of work on a custom home. The homeowner fails to pay the final invoice of $8,500. Under A.R.S. 33-981, what is the deadline to record a mechanic's lien?

Correct Answer

D) 120 days after completion of work

Under A.R.S. 33-981, mechanics' liens must be recorded within 120 days after completion of work or furnishing of materials.

Answer Options
A
90 days after completion of work
B
60 days after completion of work
C
180 days after completion of work
D
120 days after completion of work

Why This Is the Correct Answer

Under A.R.S. 33-981, a contractor must record (file) a mechanic's lien within 120 days after the last day of performing labor or furnishing materials. This 120-day window applies to original contractors. Missing this deadline extinguishes the lien right entirely.

Why the Other Options Are Wrong

Option A: 90 days after completion of work

Incorrect. 90 days is the deadline applicable to subcontractors and material suppliers in Arizona, not the original (prime) contractor. The prime contractor has 120 days. Confusing these two deadlines is a critical error.

Option B: 60 days after completion of work

Incorrect. 60 days is not a deadline specified under A.R.S. 33-981 for recording mechanic's liens in Arizona. Using this deadline would cause the contractor to miss the actual 120-day window.

Option C: 180 days after completion of work

Incorrect. 180 days is longer than the actual deadline and would mislead a contractor into thinking they have more time than they do. A.R.S. 33-981 specifies 120 days, not 180.

Memory Technique

Prime contractor = 120 days (think: '120 = 1 prime number sequence from 90'). Sub/supplier = 90 days. Remember: the prime gets an extra month (120 vs. 90). 'Prime time lasts longer β€” 120 days to lien.'

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.