A quality control plan requires concrete cylinder testing at a frequency of one set per 100 cubic yards. Your project requires 850 cubic yards of concrete. How many test sets are required?
Correct Answer
D) 9 sets
850 ÷ 100 = 8.5, which rounds up to 9 sets. Testing frequency requirements typically round up to ensure adequate coverage.
Why This Is the Correct Answer
850 ÷ 100 = 8.5, which rounds up to 9 sets. Testing frequency requirements typically round up to ensure adequate coverage.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A worker is exposed to noise levels of 95 dBA for 4 hours and 90 dBA for 4 hours during an 8-hour shift. Calculate the noise dose using OSHA's formula.
Next Question
A contractor receives a payment bond claim from a material supplier who was not paid by a subcontractor. The claim is for $28,000. What is the first step the contractor should take?
