A contractor receives a payment bond claim from a material supplier who was not paid by a subcontractor. The claim is for $28,000. What is the first step the contractor should take?
Correct Answer
A) Notify the surety company immediately
The contractor should immediately notify the surety company of any payment bond claims to ensure proper handling and protection.
Why This Is the Correct Answer
When a contractor who has provided a payment bond receives a claim against that bond, the contractor's immediate obligation is to notify the surety company. The surety issued the bond and is ultimately responsible for investigating and resolving valid claims. Prompt notification protects the contractor and activates the surety's involvement as required by the bond agreement. Failure to timely notify the surety can jeopardize the contractor's coverage.
Why the Other Options Are Wrong
Option B: Require the supplier to pursue the subcontractor first
Requiring the supplier to pursue the subcontractor first is not the contractor's role. The payment bond exists precisely to give suppliers a direct avenue for payment when subcontractors default. Directing the supplier elsewhere delays the process and may violate the bond's terms.
Option C: Verify the claim is valid and within the bond coverage
While verifying the claim's validity is important, it is not the first step β that is the surety's job after notification. Acting as investigator before notifying the surety can delay the process and create liability issues.
Option D: Pay the supplier directly and deduct from subcontractor payments
Paying the supplier directly without surety involvement could create complications regarding the contractor's subrogation rights and may not be reimbursed by the surety. This also bypasses the bond process entirely. Direct payment should only happen with surety involvement or coordination.
Memory Technique
Bond claim = surety's problem to solve. Your first move is always to NOTIFY THE SURETY. Think of the surety as your insurance company β when a claim comes in, you call your insurer first, not your checkbook.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A quality control plan requires concrete cylinder testing at a frequency of one set per 100 cubic yards. Your project requires 850 cubic yards of concrete. How many test sets are required?
Next Question
When performing takeoff for structural steel, which unit of measure is most commonly used for pricing?