EstatePass
Contract AdminProceduresmedium13% of exam part

A quality control inspection reveals that concrete strength tests show 2,800 psi when the specification requires 3,000 psi. What should be the first step in the quality control procedure?

Correct Answer

B) Document the non-conformance and notify the design professional

The first step when identifying non-conforming work is to document the issue and notify the appropriate parties, including the design professional, to determine the appropriate corrective action.

Answer Options
A
Accept the concrete since it's close to the specified strength
B
Document the non-conformance and notify the design professional
C
Immediately remove and replace all affected concrete
D
Order additional concrete testing from a different lab

Why This Is the Correct Answer

Option C is correct because proper quality control procedures require documentation and communication as the first step when non-conforming work is identified. The design professional must be notified immediately as they are responsible for determining whether the reduced strength is acceptable or what corrective measures are required. Documentation creates a paper trail for liability protection and ensures all stakeholders are aware of the issue. This follows standard construction industry protocols and legal requirements for handling specification deviations.

Why the Other Options Are Wrong

Option A: Accept the concrete since it's close to the specified strength

Option A is wrong because accepting concrete that doesn't meet specifications without proper authorization is a violation of contract requirements and could compromise structural integrity. Even though 2,800 psi is close to 3,000 psi, the contractor cannot unilaterally decide to accept non-conforming work.

Option C: Immediately remove and replace all affected concrete

Option D is wrong because while additional testing might eventually be needed, it should not be the first step. The immediate priority is to document and communicate the non-conformance. Additional testing may be part of the corrective action plan determined after consulting with the design professional.

Memory Technique

Think 'CYA' - Cover Your Assets. Always document and notify before taking action to protect yourself legally and ensure proper engineering review of structural issues.

Reference Hint

ACI 318 Building Code Requirements for Structural Concrete, Chapter 26 - Quality Control and Assurance, and Florida Building Code Chapter 19 - Concrete

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.