A property owner discovers defective work 18 months after completion. The contractor's license expired 6 months ago. What recourse does the owner have under NC law?
Correct Answer
B) Can file claim against recovery fund
Even with an expired license, property owners can file claims against the NC contractor recovery fund for defective work within the statutory period.
Why This Is the Correct Answer
NC maintains a contractor recovery fund specifically to protect consumers harmed by licensed contractors. The fund covers claims for defective work even if the contractor's license has since expired, provided the claim is filed within the statutory period. The key qualifying factor is that the contractor was licensed at the time the work was performed, not at the time the claim is filed.
Why the Other Options Are Wrong
Option A: Must pursue civil action only
Civil action alone is not the only β or necessarily primary β recourse. NC's recovery fund exists precisely to give property owners an additional, more accessible remedy beyond civil litigation, especially when contractors are difficult to collect from.
Option C: Can file complaint with licensing board only
Filing a complaint with the licensing board addresses disciplinary action against the contractor but does not directly compensate the property owner for the defective work. The recovery fund is the vehicle for financial recourse.
Option D: No recourse due to expired license
The contractor's current expired license does not strip the owner of recourse. What matters is whether the contractor held a valid license when the work was performed. NC law protects consumers in this scenario through the recovery fund.
Memory Technique
The Recovery Fund looks BACKWARD, not forward β it asks 'Was the contractor licensed when the work was done?' not 'Is the license current today?'
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass