EstatePass
Contract AdminProceduresmedium13% of exam part

A project schedule shows Activity X with early start day 15, early finish day 22, late start day 18, and late finish day 25. What is the total float for Activity X?

Correct Answer

A) 3 days

Total float is calculated as Late Start minus Early Start (or Late Finish minus Early Finish). In this case: 18 - 15 = 3 days of float, meaning Activity X can be delayed up to 3 days without affecting the project completion date.

Answer Options
A
3 days
B
10 days
C
7 days
D
15 days

Why This Is the Correct Answer

Total float represents the amount of time an activity can be delayed without affecting the project's critical path or overall completion date. The formula for total float is Late Start minus Early Start (or alternatively, Late Finish minus Early Finish). Using the given data: Late Start (18) - Early Start (15) = 3 days. This means Activity X has 3 days of scheduling flexibility before it impacts the project timeline.

Why the Other Options Are Wrong

Option C: 7 days

7 days incorrectly represents the duration of the activity (22-15=7 or 25-18=7), not the float. Duration and float are completely different concepts - duration is how long the activity takes, while float is scheduling flexibility.

Option D: 15 days

15 days is simply the early start day number, which has no relationship to float calculation. This represents when the activity can earliest begin, not the scheduling flexibility available.

Memory Technique

Remember 'LESE' - Late minus Early equals Scheduling Extra. The difference between late and early times gives you the extra time available for scheduling flexibility.

Reference Hint

Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management references, typically found in project management chapters of general contracting study guides.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.