EstatePass
Contract AdminProceduresmedium13% of exam part

A project schedule shows Activity A (4 days) must finish before Activity B (6 days) can start, and Activity B must finish before Activity C (3 days) can start. If Activity A starts on Day 1, what is the earliest finish date for Activity C?

Correct Answer

D) Day 13

Activity A: Days 1-4, Activity B: Days 5-10, Activity C: Days 11-13. Activity C finishes on Day 13, making it the earliest finish date for the sequence.

Answer Options
A
Day 12
B
Day 10
C
Day 14
D
Day 13

Why This Is the Correct Answer

This is a sequential scheduling problem where activities must be completed in order with finish-to-start relationships. Activity A runs from Day 1-4 (4 days), Activity B starts immediately after A finishes and runs from Day 5-10 (6 days), and Activity C starts immediately after B finishes and runs from Day 11-13 (3 days). The earliest finish date for Activity C is therefore Day 13.

Why the Other Options Are Wrong

Option B: Day 10

Day 14 would be incorrect because it adds an extra day beyond the required sequence. This might result from incorrectly counting days or adding unnecessary buffer time between activities.

Option C: Day 14

Day 12 falls one day short of the actual finish date. This error typically occurs from miscounting the days in one of the activities or incorrectly calculating the start/finish relationships.

Memory Technique

Use the acronym 'ADD' - Always Draw Diagrams for scheduling problems, and remember that finish-to-start means the next activity starts the day AFTER the previous one finishes.

Reference Hint

Project Management chapter covering Critical Path Method (CPM) and activity scheduling relationships

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.