EstatePass
Contract AdminPreconstructionmedium27% of exam part

A project has an estimated direct cost of $850,000. The owner requires a 15% contingency and the contract includes liquidated damages of $1,500 per day for delays beyond the 180-day completion period. What is the total project budget including contingency?

Correct Answer

B) $977,500

Contingency calculation: $850,000 × 0.15 = $127,500. Total budget: $850,000 + $127,500 = $977,500. Liquidated damages are potential costs, not included in the initial budget.

Answer Options
A
$1,247,500
B
$977,500
C
$1,127,500
D
$1,000,000

Why This Is the Correct Answer

The correct answer is A because the total project budget includes only the direct costs plus the contingency amount. The direct cost of $850,000 multiplied by the 15% contingency rate equals $127,500 in contingency funds. Adding this to the original direct cost gives us $977,500 as the total project budget. Liquidated damages are not included in the initial budget calculation as they represent potential future costs only if delays occur.

Why the Other Options Are Wrong

Option A: $1,247,500

This amount ($1,127,500) incorrectly includes additional costs beyond the required contingency, possibly mistakenly factoring in liquidated damages or using an incorrect contingency percentage.

Option C: $1,127,500

This amount ($1,247,500) is significantly higher than the correct calculation and likely includes liquidated damages or other costs that should not be part of the initial project budget.

Memory Technique

Remember 'DPC' - Direct costs Plus Contingency only. Liquidated damages are 'Later Damages' - they don't belong in the initial budget calculation.

Reference Hint

Florida Building Construction Standards - Chapter on Project Cost Estimation and Contingency Planning

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.