Under Florida Statute Chapter 713, what is the maximum time period after recording a Claim of Lien that a lienor has to file a lawsuit to enforce the lien?
Correct Answer
B) 1 year
Florida Statute 713.22 requires that a lawsuit to enforce a construction lien must be filed within one year after recording the Claim of Lien, or the lien becomes void and unenforceable.
Why This Is the Correct Answer
Florida Statute 713.22 specifically mandates that a lawsuit to enforce a construction lien must be commenced within one year after the Claim of Lien is recorded. This is a strict statutory deadline that cannot be extended or waived. If the lienor fails to file the lawsuit within this one-year period, the lien automatically becomes void and unenforceable, regardless of the validity of the underlying claim. This time limit is designed to provide certainty and prevent liens from remaining as clouds on title indefinitely.
Why the Other Options Are Wrong
Option A: 2 years
90 days is too short and is not the statutory requirement under Florida law. This timeframe might be confused with other construction-related deadlines, but it does not apply to lien enforcement lawsuits.
Option D: 90 days
2 years exceeds the statutory requirement and would allow liens to remain as clouds on title for too long. Florida law specifically limits the enforcement period to one year to balance the rights of lienors with the need for title certainty.
Memory Technique
Use the phrase 'ONE and DONE' - you have ONE year from recording to file suit, or your lien is DONE (void). Also remember: 12 months to sue = 1-2 (one year, section 713.22).
Reference Hint
Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.22 regarding enforcement of liens
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A project has an estimated direct cost of $850,000. The owner requires a 15% contingency and the contract includes liquidated damages of $1,500 per day for delays beyond the 180-day completion period. What is the total project budget including contingency?
Next Question
A commercial building project requires a Certificate of Occupancy. Which of the following is NOT typically required before CO issuance?
