North CarolinaNC Supplementmedium100% of exam part

A North Carolina contractor must file a mechanics' lien claim within how many days of last furnishing labor or materials?

Correct Answer

C) 120 days

Under NC lien law, mechanics' liens must be filed within 120 days of the last day labor or materials were furnished to the project.

Answer Options
A
180 days
B
90 days
C
120 days
D
60 days

Why This Is the Correct Answer

Under NC General Statutes § 44A-12, a mechanics' lien must be filed within 120 days of the last day on which labor or materials were furnished to the project. This 120-day window runs from the claimant's last day of performance, not from project completion or contract signing.

Why the Other Options Are Wrong

Option A: 180 days

180 days is longer than the NC statutory period. This may be confused with the deadline in some other states or with a different NC deadline (such as the 3-year statute of limitations to enforce a lien after it is filed).

Option B: 90 days

90 days is a common lien deadline in many other states (e.g., California), making it a tempting wrong answer. NC's period is 120 days, not 90.

Option D: 60 days

60 days is far too short and does not correspond to any NC mechanics' lien filing requirement. It might be confused with preliminary notice deadlines or notice of claim requirements in other states.

Memory Technique

Remember '120 = 4 months.' NC gives contractors four months (120 days) from their last day of work to file. Think of it as a 'four-month grace period' — generous enough to allow invoicing disputes to play out before filing.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.