EstatePass
North CarolinaNC Supplementmedium100% of exam part

A North Carolina contractor fails to pay subcontractors $45,000 on a residential project. Under NC lien law, what is the maximum time period after substantial completion that a subcontractor has to file a claim of lien on real property?

Correct Answer

C) 120 days

Under NC lien law, subcontractors have 120 days from substantial completion to file a claim of lien on real property.

Answer Options
A
60 days
B
180 days
C
120 days
D
90 days

Why This Is the Correct Answer

Under NC General Statutes Chapter 44A, subcontractors have 120 days from the last furnishing of labor or materials (or from substantial completion) to file a Claim of Lien on Real Property. Missing this deadline extinguishes the lien right permanently.

Why the Other Options Are Wrong

Option A: 60 days

60 days is too short β€” that is not the NC statutory deadline for filing a lien claim. Confusing this with other states' lien deadlines or with notice requirements is common.

Option B: 180 days

180 days is too long and is not the NC deadline for filing a lien claim on real property. It may be confused with the time to enforce (file suit) on a perfected lien, which has a separate longer deadline.

Option D: 90 days

90 days is not the NC deadline. While some states use 90 days, North Carolina specifically requires 120 days. This distractor targets candidates who guess based on general knowledge rather than NC-specific law.

Memory Technique

120 days = 4 months. Think: a subcontractor has a full season (one quarter of the year plus one month) to file after substantial completion. '4 months to file' is your anchor.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.