A Nevada contractor's bond is in the amount of $50,000. The contractor defaults on three separate projects with damages of $25,000, $18,000, and $12,000 respectively. What is the maximum total amount that can be recovered from the bond?
Correct Answer
B) $50,000
The bond amount of $50,000 is the maximum that can be recovered regardless of the total claims amount ($55,000).
Why This Is the Correct Answer
A surety bond is a fixed pool of funds. The bond amount — $50,000 — is the absolute ceiling for all combined claims. Total damages of $55,000 exceed the bond, so claimants can collectively recover no more than $50,000, prorated if necessary.
Why the Other Options Are Wrong
Option A: $65,000
$65,000 exceeds both the bond amount and the total damages, making it impossible to recover from the bond. This figure has no basis in the scenario.
Option C: $55,000
$55,000 is the sum of all three claims ($25,000 + $18,000 + $12,000) but it exceeds the bond amount. The bond caps recovery at $50,000 regardless of actual damages.
Option D: $43,000
$43,000 represents only two of the three claims ($25,000 + $18,000), which is an incomplete and arbitrary calculation with no legal basis.
Memory Technique
A bond is like a bucket — once it's empty, it's empty. No matter how many claims pour in, you can only take out what's in the bucket ($50,000).
More Nevada Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?