A Nevada contractor completes work valued at $85,000 on March 15th. Under NRS 108, what is the deadline for filing a mechanic's lien if no notice of completion is recorded?
Correct Answer
D) September 15th
Under NRS 108.226, a mechanic's lien must be filed within 6 months after completion of work when no notice of completion is recorded.
Why This Is the Correct Answer
Under NRS 108.226, when no notice of completion is recorded by the owner, a prime contractor has 6 months from the date of completion to file a mechanic's lien. March 15th + 6 months = September 15th.
Why the Other Options Are Wrong
Option A: June 15th
June 15th is exactly 3 months after March 15th β this corresponds to the 90-day rule in some contexts, but the question specifically asks about the scenario where no notice of completion is recorded, which triggers the 6-month (180-day) period.
Option B: May 15th
May 15th is only 2 months after March 15th, which corresponds to the 60-day window for subcontractors when a notice of completion HAS been recorded β not the applicable rule here.
Option C: March 15th of the following year
March 15th of the following year would be 12 months β there is no 1-year lien filing window under NRS 108 in this context.
Memory Technique
No notice = more time. Think of it as the owner's job to record the notice; if they don't do their part, the contractor gets a longer window β 6 months (September for a March completion).
More Nevada Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass