EstatePass
nv-supplementNevada Business & Lawmedium

A Nevada contractor completes work valued at $85,000 on March 15th. Under NRS 108, what is the deadline for filing a mechanic's lien if no notice of completion is recorded?

Correct Answer

D) September 15th

Under NRS 108.226, a mechanic's lien must be filed within 6 months after completion of work when no notice of completion is recorded.

Answer Options
A
June 15th
B
May 15th
C
March 15th of the following year
D
September 15th

Why This Is the Correct Answer

Under NRS 108.226, a mechanic's lien must be filed within 6 months after completion of work when no notice of completion is recorded.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.