A Nevada contractor completes a $85,000 kitchen remodel. The homeowner refuses to pay the final $12,000, claiming defective work. How long does the contractor have to file a lien after the work was completed?

Correct Answer

C) 90 days

Under NRS 108, contractors have 90 days from completion of work to file a mechanic's lien.

Answer Options
A
120 days
B
60 days
C
90 days
D
180 days

Why This Is the Correct Answer

Under NRS 108, contractors have 90 days from completion of work to file a mechanic's lien.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.