EstatePass
MichiganBusinesshard50% of exam part

A Michigan contractor files a construction lien for $25,000. Under the Construction Lien Act 497, within how many days must the contractor commence legal action to enforce the lien?

Correct Answer

C) 365 days

Under Michigan's Construction Lien Act 497, legal action to enforce a construction lien must be commenced within one year (365 days) of filing the lien.

Answer Options
A
120 days
B
180 days
C
365 days
D
90 days

Why This Is the Correct Answer

Michigan's Construction Lien Act 497 gives a lien claimant one year (365 days) from the date the lien was recorded to commence a civil action to enforce it. Failure to file suit within this period causes the lien to expire and become unenforceable, eliminating the contractor's security interest in the property.

Why the Other Options Are Wrong

Option A: 120 days

120 days is not the enforcement deadline under Michigan's Construction Lien Act. This figure may be confused with other construction law timeframes (such as notice periods), but it is not the statutory window for filing suit to enforce a lien.

Option B: 180 days

180 days (6 months) is not the correct period. Some candidates associate this with other states' lien laws or with the Notice of Furnishing timeline. Michigan's Act 497 sets a full one-year window for enforcement actions.

Option D: 90 days

90 days is not the enforcement deadline. While 90 days is a commonly referenced period in construction law (such as the time to file a lien after last furnishing labor/materials), it does not govern how long a contractor has to sue to enforce the lien after filing.

Memory Technique

Two timelines to memorize for Michigan liens: '90 days to FILE, 365 days to FIGHT.' File the lien within 90 days of your last work; then you have one full year from filing to take it to court.

Was this explanation helpful?

More Michigan Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.