A Michigan contractor completes work on March 15th. The property owner records a Notice of Completion on March 22nd. Under the Construction Lien Act 497, by what date must the contractor file a construction lien?

Correct Answer

C) April 21st

When a Notice of Completion is recorded, contractors have 30 days from the recording date to file a lien. March 22nd + 30 days = April 21st.

Answer Options
A
May 22nd
B
May 15th
C
April 21st
D
June 15th

Why This Is the Correct Answer

Under Michigan's Construction Lien Act, once a Notice of Completion is recorded by the property owner, contractors and subcontractors have only 30 days from the recording date to file a lien — a shorter window than the standard 90 days from last date of furnishing. The Notice of Completion was recorded March 22nd; adding 30 days gives a deadline of April 21st.

Why the Other Options Are Wrong

Option A: May 22nd

May 22nd would be 60 days after the Notice of Completion recording date (March 22nd), which is incorrect. The accelerated deadline triggered by a Notice of Completion is 30 days, not 60.

Option B: May 15th

May 15th is 60 days from the completion of work (March 15th), also incorrect. When a Notice of Completion is recorded, the 30-day clock from that recording date governs — not 60 days from work completion.

Option D: June 15th

June 15th is 90 days from the work completion date (March 15th), which would be the standard deadline if no Notice of Completion had been recorded. Because a Notice of Completion was filed, the 30-day rule applies and the deadline is much earlier.

Memory Technique

Notice of Completion = 30-day sprint. Once the owner files that notice, the contractor must run — only 30 days from the recording date. March 22nd + 30 = April 21st. Think '30 from the notice, not 90 from the work.'

Was this explanation helpful?

More Michigan Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.