A material supplier delivers $45,000 worth of materials to a Nevada construction project. The general contractor fails to pay. What is the maximum lien amount the supplier can claim?
Correct Answer
D) $45,000 (full amount)
Under NRS 108, a material supplier can claim a lien for the full amount of materials furnished to the project, which is $45,000.
Why This Is the Correct Answer
NRS 108 entitles a material supplier to file a mechanic's lien for the exact value of materials furnished to the project — no more, no less. The supplier delivered $45,000 in materials, so the maximum lien is $45,000. Nevada lien law is compensatory, not punitive: it restores what was owed, not a penalty amount.
Why the Other Options Are Wrong
Option A: $54,000 (materials plus 20% penalty)
A 20% penalty on top of the materials value ($54,000) has no basis in NRS 108. Mechanic's lien statutes are compensatory, not punitive — they allow recovery of the amount owed for goods furnished, not an inflated penalty figure.
Option B: $49,500 (materials plus 10% interest)
$49,500 adds a 10% interest component to the principal. While interest may be recoverable through a separate legal action, it is not included in the lien amount itself under NRS 108. The lien is limited to the value of materials delivered.
Option C: $40,500 (90% of materials)
$40,500 (90% of materials) has no legal basis. There is no statutory reduction applied to lien claims for material suppliers under NRS 108. This distractor likely preys on confusion with retainage provisions, which apply to contract payments, not lien calculations.
Memory Technique
The lien is a mirror of what you're owed. '$45,000 delivered = $45,000 lien.' Think of it as a legal receipt — you can only claim what the receipt says.
More Nevada Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor has a workers' compensation experience modification factor of 1.15. If the base premium is $12,000, what is the adjusted premium?
Next Question
An employee is injured on a Nevada construction site. The contractor's workers' compensation coverage has lapsed. What is the contractor's potential liability?
