EstatePass
ArizonaAZ B&Lhard100% of exam part

A material supplier delivered $12,000 worth of materials over a 3-month period. The last delivery was made on May 20th. What is the deadline for filing a preliminary 20-day notice?

Correct Answer

A) The deadline has passed

The preliminary 20-day notice must be served within 20 days of first furnishing materials, not the last delivery. Since materials were delivered over 3 months, the deadline has passed.

Answer Options
A
The deadline has passed
B
May 30th
C
June 20th
D
June 9th

Why This Is the Correct Answer

Arizona's preliminary 20-day notice (A.R.S. § 33-992.01) must be served within 20 days of FIRST furnishing labor or materials — not the last delivery. Because the supplier delivered materials over a 3-month period, the 20-day window from the first delivery expired long before May 20th. The deadline has already passed, and the supplier can no longer preserve lien rights for the full amount delivered during that period.

Why the Other Options Are Wrong

Option B: May 30th

May 30th would be 20 days after the last delivery (May 20 + 10 days). This calculation incorrectly uses the last delivery date rather than the first delivery date as the trigger.

Option C: June 20th

June 20th would be 31 days after the last delivery. This misapplies both the trigger date and the 20-day period, treating it as a calendar-month window from the last delivery.

Option D: June 9th

June 9th is 20 days after May 20th. Again, this uses the last delivery as the trigger event, which is incorrect under Arizona law.

Memory Technique

'First in, 20 days out.' The notice clock starts ticking the moment the FIRST material arrives on site. Think of it as a 20-day countdown that begins at delivery #1, not delivery #last.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.