EstatePass
Contract AdminProcedureseasy13% of exam part

A LEED project requires tracking the recycled content of materials. The project uses 1000 tons of concrete with 20% fly ash content and 500 tons of steel with 90% recycled content. What is the total weight of recycled content materials?

Correct Answer

A) 650 tons

Concrete recycled content: 1000 tons × 20% = 200 tons. Steel recycled content: 500 tons × 90% = 450 tons. Total recycled content: 200 + 450 = 650 tons.

Answer Options
A
650 tons
B
200 tons
C
1350 tons
D
450 tons

Why This Is the Correct Answer

Option C is correct because it properly calculates the recycled content for each material separately and then sums them. For concrete: 1000 tons × 20% = 200 tons of recycled content (fly ash). For steel: 500 tons × 90% = 450 tons of recycled content. The total recycled content is 200 + 450 = 650 tons, which represents the actual weight of recycled materials used in the project.

Why the Other Options Are Wrong

Option C: 1350 tons

Option A only accounts for the recycled content in concrete (200 tons) but completely ignores the recycled content in steel (450 tons), resulting in an incomplete calculation.

Option D: 450 tons

Option B only accounts for the recycled content in steel (450 tons) but ignores the recycled content from the fly ash in concrete (200 tons), missing a significant portion of the total.

Memory Technique

Remember 'PTA' - Percentage × Total = Amount for each material, then Add all amounts together. Don't confuse total material weight with recycled content weight.

Reference Hint

LEED Reference Guide for Building Design and Construction, Materials and Resources section, or Florida Building Code Chapter on Sustainable Construction practices

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.