A general contractor is building a 50,000 square foot warehouse. The building permit fee is calculated at $8.50 per 1,000 square feet or fraction thereof. What is the total permit fee?
Correct Answer
D) $425.00
50,000 ÷ 1,000 = 50 units. 50 × $8.50 = $425.00. Since there's no fraction, the calculation is straightforward.
Why This Is the Correct Answer
The calculation correctly divides the total square footage by 1,000 to determine the number of billing units (50,000 ÷ 1,000 = 50). Since 50,000 divides evenly by 1,000, there is no fraction to round up. The fee is then calculated by multiplying 50 units by $8.50 per unit, resulting in $425.00. This follows the standard permit fee calculation method used in Florida construction.
Why the Other Options Are Wrong
Option B: $450.00
This answer ($450.00) appears to come from incorrectly using a rate of $9.00 per 1,000 square feet, which is not the rate specified in the problem.
Option C: $500.00
This answer ($400.00) would result from incorrectly using a rate of $8.00 per 1,000 square feet instead of the given $8.50 rate, or from miscalculating 50 × $8.50.
Memory Technique
Remember 'Divide, Check for fractions, Multiply' - DCM method for permit fee calculations
Reference Hint
Florida Building Code, Chapter 1 - Scope and Administration, Section on Permits and Fees
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A LEED project requires tracking the recycled content of materials. The project uses 1000 tons of concrete with 20% fly ash content and 500 tons of steel with 90% recycled content. What is the total weight of recycled content materials?
Next Question
For LEED certification, which of the following best describes the 'commissioning' process?
