EstatePass
Contract AdminProceduresmedium13% of exam part

A LEED project requires the use of materials with recycled content. The project uses 1000 tons of structural steel containing 25% recycled content and 500 tons of concrete with 15% fly ash content. What is the total weight of recycled/sustainable materials?

Correct Answer

D) 325 tons

Steel recycled content: 1000 tons × 25% = 250 tons. Concrete fly ash content: 500 tons × 15% = 75 tons. Total recycled/sustainable materials: 250 + 75 = 325 tons.

Answer Options
A
375 tons
B
250 tons
C
175 tons
D
325 tons

Why This Is the Correct Answer

Option C is correct because it properly calculates the recycled content from both materials and adds them together. The structural steel contributes 250 tons of recycled content (1000 × 0.25), and the concrete contributes 75 tons of fly ash content (500 × 0.15). The total sustainable/recycled material weight is 250 + 75 = 325 tons.

Why the Other Options Are Wrong

Option A: 375 tons

This answer appears to add incorrect percentages or double-count some materials, resulting in an inflated total that exceeds the correct calculation.

Option B: 250 tons

This answer only includes the recycled content from structural steel (250 tons) but fails to add the fly ash content from the concrete.

Memory Technique

Remember 'PART + PART = WHOLE' - calculate the recycled PART of each material type, then add all PARTS together for the WHOLE recycled content total.

Reference Hint

LEED Reference Guide for Building Design and Construction, Materials and Resources section, or Florida Building Code Chapter 11 - Energy Efficiency

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.