EstatePass
Contract AdminPreconstructionhard27% of exam part

A contractor is evaluating whether to rent or buy a bulldozer. The purchase price is $250,000 with a 7-year life. Rental cost is $3,200 per month. At what point does purchasing become more economical than renting?

Correct Answer

C) After 65 months

Break-even point = Purchase price ÷ Monthly rental = $250,000 ÷ $3,200 = 78 months. However, considering depreciation and the equipment's useful life, the actual break-even considering salvage value would be around 65 months.

Answer Options
A
After 18 months
B
After 6 months
C
After 65 months
D
After 36 months

Why This Is the Correct Answer

Option D is correct because the break-even analysis must consider both the rental costs and the equipment's depreciation/salvage value over its useful life. While the simple calculation gives 78 months ($250,000 ÷ $3,200), the equipment has a 7-year (84-month) useful life and will retain some salvage value. When factoring in the equipment's residual value at the end of its useful life, the true break-even point occurs around 65 months, making purchasing economical after this point.

Why the Other Options Are Wrong

Option A: After 18 months

18 months represents only $57,600 in rental costs, which is less than 25% of the purchase price and nowhere near the break-even point.

Option B: After 6 months

36 months equals $115,200 in rental costs, which is less than half the purchase price and still well short of the break-even point.

Option D: After 36 months

6 months is far too short a period to recover a $250,000 investment with $3,200 monthly rental savings, representing only $19,200 in rental costs.

Memory Technique

Remember 'SALVAGE' - Simple calculation Always Lacks Value Assessment, so Gauge Equipment's residual worth to find true break-even.

Reference Hint

Construction project management texts, Chapter on Equipment Economics and Cost Analysis, or Business and Finance sections covering lease vs. buy decisions

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.