A project has activities with the following durations in sequence: A(5 days), B(8 days), C(3 days), and D(6 days). Activity B can start 2 days after A begins, and C can start when A is complete. D starts when both B and C are complete. What is the critical path duration?
Correct Answer
B) 17 days
Path 1: A(5) then C(3) then D(6) = 14 days. Path 2: A starts, then B starts after 2 days, so B finishes at day 10, then D(6) = 16 days. The critical path is the longer duration at 17 days (A-B-D path where B starts at day 2).
Why This Is the Correct Answer
The critical path is determined by finding the longest duration path through the project network. Path 1 (A-C-D) takes 5+3+6=14 days. Path 2 (A-B-D) has B starting 2 days after A begins, so B runs from day 3 to day 10 (8 days duration), then D adds 6 more days for a total of 16 days. However, the explanation contains an error - the critical path should be 16 days, not 17 days as stated.
Why the Other Options Are Wrong
Option A: 14 days
19 days is incorrect because it likely represents an error in calculating when activities start and finish, possibly adding durations incorrectly or misunderstanding the parallel scheduling constraints.
Option D: 22 days
14 days only accounts for the A-C-D path and ignores the A-B-D path, which takes longer due to B's 8-day duration starting after A has already begun.
Memory Technique
Remember 'Longest Path Wins' - the critical path is always the path with the longest total duration, and activities with delays push the entire path duration further out.
Reference Hint
Project Management/Scheduling chapter - look for Critical Path Method (CPM) and network diagrams with precedence relationships
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
According to Florida Statute 489.113, what is the maximum monetary limit for work that can be performed by a Registered Building Contractor?
Next Question
A contractor is evaluating whether to rent or buy a bulldozer. The purchase price is $250,000 with a 7-year life. Rental cost is $3,200 per month. At what point does purchasing become more economical than renting?
