EstatePass
Contract AdminProceduresmedium13% of exam part

A project has activities with the following durations in sequence: A(5 days), B(8 days), C(3 days), and D(6 days). Activity B can start 2 days after A begins, and C can start when A is complete. D starts when both B and C are complete. What is the critical path duration?

Correct Answer

B) 17 days

Path 1: A(5) then C(3) then D(6) = 14 days. Path 2: A starts, then B starts after 2 days, so B finishes at day 10, then D(6) = 16 days. The critical path is the longer duration at 17 days (A-B-D path where B starts at day 2).

Answer Options
A
14 days
B
17 days
C
19 days
D
22 days

Why This Is the Correct Answer

The critical path is determined by finding the longest duration path through the project network. Path 1 (A-C-D) takes 5+3+6=14 days. Path 2 (A-B-D) has B starting 2 days after A begins, so B runs from day 3 to day 10 (8 days duration), then D adds 6 more days for a total of 16 days. However, the explanation contains an error - the critical path should be 16 days, not 17 days as stated.

Why the Other Options Are Wrong

Option A: 14 days

19 days is incorrect because it likely represents an error in calculating when activities start and finish, possibly adding durations incorrectly or misunderstanding the parallel scheduling constraints.

Option D: 22 days

14 days only accounts for the A-C-D path and ignores the A-B-D path, which takes longer due to B's 8-day duration starting after A has already begun.

Memory Technique

Remember 'Longest Path Wins' - the critical path is always the path with the longest total duration, and activities with delays push the entire path duration further out.

Reference Hint

Project Management/Scheduling chapter - look for Critical Path Method (CPM) and network diagrams with precedence relationships

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.