EstatePass
Contract AdminContractseasy40% of exam part

Under Florida Statute Chapter 713, when must a Notice to Owner be served on a private project?

Correct Answer

D) Within 45 days of first furnishing labor or materials

Florida Chapter 713 requires that a Notice to Owner be served within 45 days of first furnishing labor, services, or materials to the project. This notice is essential for preserving lien rights.

Answer Options
A
Within 60 days of project completion
B
Before any work begins on the project
C
Within 30 days of first furnishing labor or materials
D
Within 45 days of first furnishing labor or materials

Why This Is the Correct Answer

Florida Statute Chapter 713 specifically mandates that a Notice to Owner must be served within 45 days of first furnishing labor, services, or materials to a private construction project. This 45-day requirement is a critical statutory deadline that protects the lienor's right to claim a construction lien. Failure to serve this notice within the prescribed timeframe can result in the complete loss of lien rights, making compliance with this deadline essential for contractors and suppliers.

Why the Other Options Are Wrong

Option A: Within 60 days of project completion

30 days is too short and does not comply with Florida Statute Chapter 713 requirements. This timeframe would create unnecessary urgency and potential hardship for contractors who need adequate time to identify property owners and serve proper notice.

Option B: Before any work begins on the project

60 days after project completion is far too late and completely defeats the purpose of the Notice to Owner, which is to inform property owners of potential lienors during the active construction phase, not after the project is finished.

Option C: Within 30 days of first furnishing labor or materials

Requiring notice before work begins would be impractical and is not what the statute requires. Many subcontractors and suppliers are brought onto projects after work has already commenced, and this timing would make it impossible for them to preserve their lien rights.

Memory Technique

Remember 'Forty-Five to stay alive' - your lien rights stay alive only if you serve Notice to Owner within 45 days of first furnishing labor or materials.

Reference Hint

Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.06 regarding Notice to Owner requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.