EstatePass
South CarolinaSC Supplementhard100% of exam part

A homeowner hired a contractor for a $45,000 kitchen renovation. The contractor completed 80% of the work before abandoning the project. Under SC law, what is the contractor's maximum exposure for actual damages if the homeowner must pay another contractor $15,000 to complete the work?

Correct Answer

A) $15,000

The contractor is liable for the actual damages incurred by the homeowner, which is the $15,000 cost to complete the work.

Answer Options
A
$15,000
B
$9,000
C
$12,000
D
$36,000

Why This Is the Correct Answer

Option A is correct. Under SC law, the contractor's liability for actual damages is measured by the cost incurred by the homeowner as a direct result of the breach — specifically, the $15,000 cost to hire another contractor to complete what was abandoned. Actual damages are the economic loss directly caused by the breach, not a percentage of the original contract or the value of work completed.

Why the Other Options Are Wrong

Option B: $9,000

Option B is incorrect. $9,000 appears to be derived from 60% of the remaining 20% of work ($45,000 × 20% × some factor), but this calculation has no legal basis under SC contract law. Damages are not computed as a percentage discount on the unfinished portion.

Option C: $12,000

Option C is incorrect. $12,000 does not correspond to any standard legal measure of actual damages in this scenario. It falls between $9,000 and $15,000 without a logical derivation from the facts given.

Option D: $36,000

Option D is incorrect. $36,000 represents 80% of the contract price (the value of work completed), not the homeowner's actual loss. The homeowner already received 80% of the work — their loss is only the additional cost to complete the remaining 20%, which is $15,000.

Memory Technique

Remember: 'Actual damages = what it costs to fix the breach.' In abandonment cases, ask: 'What did the homeowner have to spend because of the contractor's failure?' That expenditure — $15,000 to complete — is the actual damage. The contractor gets no 'credit' deduction for work already done when calculating the owner's out-of-pocket loss from the breach.

Was this explanation helpful?

More South Carolina Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.