A contractor's general liability policy has a $2 million aggregate limit and $1 million per occurrence limit. After two claims of $800,000 each, how much coverage remains?
Correct Answer
A) $400,000
Aggregate limit applies to total claims per policy period: $2,000,000 - ($800,000 + $800,000) = $400,000 remaining.
Why This Is the Correct Answer
The aggregate limit is the maximum the policy will pay for all claims combined during the policy period. Two claims totaling $1,600,000 are subtracted from the $2,000,000 aggregate: $2,000,000 − $1,600,000 = $400,000 remaining. Each claim ($800,000) was within the $1 million per-occurrence limit, so both were paid in full.
Why the Other Options Are Wrong
Option B: $600,000
$600,000 would result from subtracting only one $800,000 claim from the remaining balance after misapplying the per-occurrence limit, or from using an incorrect starting total.
Option C: $1,000,000
$1,000,000 incorrectly treats the per-occurrence limit as the remaining aggregate, ignoring that two separate claims have already been paid from the aggregate pool.
Option D: $200,000
$200,000 results from subtracting $1,800,000 total instead of $1,600,000, or from incorrectly capping each claim at a different amount.
Memory Technique
Aggregate = the bucket. Per occurrence = the biggest single scoop. Each claim ($800K) fits within the $1M scoop limit, so both are paid in full from the bucket: $2M − $0.8M − $0.8M = $0.4M left in the bucket.
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A homeowner hired a contractor for a $45,000 kitchen renovation. The contractor completed 80% of the work before abandoning the project. Under SC law, what is the contractor's maximum exposure for actual damages if the homeowner must pay another contractor $15,000 to complete the work?
Next Question
A Tier I contractor completes a $45,000 addition but the final cost reaches $52,000 due to change orders. What is the potential penalty?
