EstatePass
sc-supplementSC State Supplementhard

A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?

Correct Answer

D) Lien rights limited to unpaid amount

In South Carolina, subcontractors have lien rights for the actual unpaid amount of their work, regardless of payments between owner and general contractor.

Answer Options
A
Lien rights only after general contractor files
B
Lien rights equal to general contractor
C
No lien rights since not in direct contract with owner
D
Lien rights limited to unpaid amount

Why This Is the Correct Answer

Under South Carolina mechanics' lien law, subcontractors have direct lien rights against the property for the actual unpaid amount of their work performed. The subcontractor's lien is limited to the specific dollar amount they are owed ($25,000 in this case), regardless of what the general contractor was paid by the owner. This protects subcontractors while ensuring liens don't exceed actual damages suffered.

Why the Other Options Are Wrong

Option A: Lien rights only after general contractor files

Subcontractors have independent lien rights that don't depend on the general contractor filing first. They can file their own lien directly against the property for unpaid work without waiting for or requiring any action from the general contractor.

Option B: Lien rights equal to general contractor

While subcontractors do have lien rights, they are not necessarily equal to the general contractor's rights. The subcontractor's lien is specifically limited to their unpaid amount, whereas the general contractor might have different lien amounts or priorities based on their total contract value.

Option C: No lien rights since not in direct contract with owner

South Carolina law grants subcontractors direct lien rights against the property even without a direct contract with the owner. The lack of privity with the owner doesn't eliminate lien rights - subcontractors can still lien for their unpaid work performed on the property.

Memory Technique

Remember 'LIMIT': Lien rights are Limited to the actual unpaid amount - you can't lien for more than what you're actually owed.

Was this explanation helpful?

More sc-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.